In 2016, Class was contracted to have a complete operational camp of a military command based at Al Minhad AB, Dubai UAE. While the contract stipulated 60 days for the complete move, Class was faced with a peculiar challenge.

The command needed to be fully operational on the new camp site within 40 days as there was a deadline to vacate the old premises.

The Class machinery kicked into full gear and deployed separate teams for the laying of the surface (grading, compaction, asphalting), setting up of pipelines (Electrical, Water, Sewage, Comms) and movement of 23 portable office buildings.

The area was fully operational on the 38th day and the Class team received a personal commendation from the military command.